26.04.2024
Progress of work on 11-meters motor yacht.
Work continues on laying flexitik on the external decks.
Electrical wiring, piping and a pump for the deck shower in the cockpit were installed.
The first finishing panel has been installed in the rear right window frame. After the final fit, the frames will be covered by Novatex.
Electrical wiring has been installed in the roof to connect the radar, navigation lights and interior lighting.

The boiler is installed, electrical wiring is connected to it, an expansion tank and a pump are installed.
Radar arch and shock-absorbing pedestal in cutting and bending.
In the upcoming holiday week, ready-made cabinets are expected to arrive at the shipyard. Installing Zeepwake. Installation of plumbing equipment in the toilet.